Brooklyn · NYC SIDEWALK SHED RECORD
878 Park Avenue
Sidewalk shed permits, reported ownership and façade history for 878 Park Avenue, Brooklyn, New York City.
0.9 years since the first permit of the oldest currently active shed job: . Permit age does not establish continuous physical presence or inactivity.
Snapshot: . BIN 3326366 · Tax lot 3015800001.
Repairs required; removal not confirmed
The 2026-07-27 filing says SWARMP: safe with a repair and maintenance program. It does not confirm that repairs are finished.
The incentive to put repairs off
A large repair bill can be harder to fund than ongoing shed rent. NYC officials have identified that incentive to delay, while pedestrians and businesses live with the shed. Rent does not replace the duty to repair or pay applicable penalties. Research, rules and examples
The interactive page compares dated repair budgets and recorded enforcement where available. These are not verified savings or evidence of this owner’s motive.
Reported building owner
NYCHA — named in a façade filing dated 2026-07-27. This is dated attribution, not verified current title or beneficial ownership.
Read the owner sourceLatest dated façade classification
SWARMP · 2026-07-27 · Cycle 10. Safe with a repair and maintenance program; this does not mean all work is complete.
Read the façade sourceActive sidewalk shed permits
- B01318189-I1 — first permitted 2025-12-09; listed expiration 2026-12-09; status Permit Entire; reported length 56 ft.
DOB active-shed source · Summed lengths may overlap.
Façade filing history
- 2026-07-27T00:00:00.000 — SWARMP, cycle 10. Inspect filing TR6-1009350-10B-A1
- 2026-04-09T00:00:00.000 — UNSAFE, cycle 10. Inspect filing TR6-1009350-10B-I1
- 2022-08-17T00:00:00.000 — SWARMP, cycle 9. Inspect filing TR6-909350-9B-I1
- 2021-10-13T00:00:00.000 — SAFE, cycle 8. Inspect filing TR6-809350-8B-A1
- 2019-06-13T00:00:00.000 — UNSAFE, cycle 8. Inspect filing TR6-809350-8B-I2
- 2013-08-09T00:00:00.000 — UNSAFE, cycle 7. Inspect filing TR6-709350-7B-I1
- 2012-02-28T00:00:00.000 — UNSAFE, cycle 6. Inspect filing TR6-609350-NA-S1
- 2010-02-22T00:00:00.000 — UNSAFE, cycle 6. Inspect filing TR6-609350-NA-I1
What remains unknown
These records do not independently establish continuous shed presence, daily repair activity, approved extensions, actual repair costs or owner intent. The interactive page can request additional repair and summons records; source failures and incomplete coverage are labeled.
Open the DOB building profile · Explore the economics of delay